Work Progress

District:

SUMMARY SHEET OF CONTRACTS

Ref

Brief Description

Type

Start date

End date

Total Value (NRs.)

Paid to date (NRs.)

On target? (Y/N)

Key issues or actions required

Contract1

Clearing Land slides, pot holes and repairing works

Emergency

9 Nov 2014

9 Dec 2014

355,496.60

355,496.60

N

Completed

Contract2

Clearing Land slides, pot holes and repairing works

Emergency

9 Nov 2014

9 Dec 2014

249,944.25

249,944.25

N

Completed

Contract3

Clearing Land slides, pot holes and repairing works

Emergency

9 Nov 2014

9 Dec 2014

198,836.10

198,836.10

N

Completed

Contract 4

Clearing Land slides, pot holes and repairing works

Emergency

9 Nov 2014

9 Dec 2014

204,983.75

204,983.75

N

Completed

Contract 5

Earthwork excavation in foundation, Gabion wall, Dry stone soling, back filling and earthen side drain

Specific

19  May 2015

15 Dec 2015

1,246,684.20

124,000

Y

On going

Contract 6

Earthwork excavation in foundation, Gabion wall, Dry stone soling, back filling and earthen side drain

Specific

25 May 2015

17 Oct 2015

1,162,706.20

913,889

Y

On going

Contract 7

Earthwork excavation in foundation, Gabion wall, Dry stone soling, back filling and earthen side drain

Specific

26 May 2015

17 Oct 2015

1,624,729.85

1,624,477.35

Y

Completed

Contract 8

Earthwork excavation in foundation, Gabion wall, Dry wall, Dry stone soling, back filling and earthen side drain

Specific

18 May 2015

17 Oct 2015

1,300,203.20

1,013,169.28

Y

On going

Contract 9

Earthwork excavation in foundation, Gabion wall, Dry stone soling, back filling and earthen side drain

Specific

27 May 2015

15 Dec 2015

742,000

168,532.10

Y

Through UC, on going

Contract 10

Earthwork excavation in foundation, Gabion wall, Dry stone soling and back filling

Specific

19 May 2015

15 Dec 2015

759,938.26

75,900

Y

On going

Contract 11

Earthwork excavation in foundation, Gabion wall and back filling

Specific

19 May 2015

15 Dec 2015

676,611.49

67,600

Y

On going

Contract 12

Earthwork excavation in foundation, Gabion wall, Dry stone soling, back filling and earthen side drain

Specific

27 May 2015

15 Dec 2015

649,863.50

 

Y

On going

Contract 13

Earthwork excavation in foundation, Gabion wall, Dry stone soling and back filling

Specific

19 May 2015

17 Oct 2015

503,000.45

424,188.43

Y

On going