RMG public audit and refresher training at Achham

By RAP 3 on June 18, 2018

District:

DTA Achham has successfully completed cluster level RMG Public Audit and refresher training at three different clusters. Audits at Sanfebagar, Mangalsen and Kamalbazar clusters were conducted on 14th, 15th and 17th June 2018 respectively. Representatives from DCC/DTO and Technical Focal Person from respective R/RMs were present at the programme. The first part of the programme was refresher training about group formation, monthly work plan were delivered. RMGs were also informed about the ongoing handover of RMGs to local levels. The next session of the programme was a public audit session where wages received by RMGs in FY 074-75 were audited. The Chairperson of each RMGs presented the amount of received wages while the rest of the members were asked if they had any grievances. No major grievances were identified and the audit finished a vote of thanks by the participants and closing speech by the chairperson.

RMG management Handover Training to local levels

By RAP 3 on May 18, 2018

District:

DTA Achham successfully conducted RMGs management handover training to Technical focal person (TFP) of Municipalities/Rural municipalities on 15th and 16th May 2018. The first day of training was the theoretical session where nine modules such as RMG formation and contracting system, RMG Guideline and detail operation and RMG perspective from GoN were covered. The modules were delivered by DTO, DC, RTL, GE and Jr. IoW. Next day of the training was the practical session where TFPs inspected the work of previous month’s work plan of nearby RMG (69DR011) and provided the work plan for next month. At the end of the training, TFPs presented on their understandings of RMG formation, inspection and payment process. TFPs are expected to conduct supervision of RMGs works and certify their bills which is considered to be a vital step towards handover of RMGs to local levels.

Final Payment to Kalikadevi SMG in Achham

By RAP 3 on April 11, 2018

District:

After successful completion of 99% of total construction works, RAP3 DTA Achham has made final payment to Kalikadevi SMG at 69DR011 (Mangalsen -Chitre -Payal-Siudi). Total agreement amount with this group was NRs. 576,592 out of which NRs. 505,695 was allocated for construction cost. This group started their work at the end of December 2017 and completed ahead of the expected completion date. The specific maintenance work included construction of gabion retaining walls, dry stone soling and dry stone wall. Final payment of wages was distributed among all group member in presence of DTA representatives. All SMG members, women in particular, were very glad to receive equal wage payment based on wage rate higher than the district wage rate. Of total 13 members, 5 members were females in this SMG.

First Interim Payment to SMG

By RAP 3 on February 23, 2018

District:

DTA Achham has released Interim Payment (IPC-1) to all five Specific Maintenance Groups (SMG) on 18th February 2018. As per the agreement, 80% of construction work completed was included in this payment. The payment was distributed in presence of site-in-charge among all group members. Total payment of NRs. 1,084,765 was released to all SMG groups. On average, 31% of total work in all SMGs has been completed with highest progress of 46% in Devkanya ‘B’ SMG of 69DR003 road.

Skilled women workforce in Achham

By RAP 3 on February 9, 2018

District:

‘Laganshil’ group - a Specific Maintenance Group (SMG) working at 69DR018 – consists of 16 members, out of which 12 members (75%) are females. With the experience gained while working in SMG, most of the female members in this group have gained skills in construction of road infrastructure such as gabion and dry stone retaining wall. This group was formed last year in the first year of SMG piloting. ‘Surja Rawol’ (Chairperson of this SMG) says that initially locals were not convinced they could perform work as skilled manpower. She added her group was highly motivated to complete contracted specific maintenance works last year just to prove that women can also become part of a skilled workforce. Ultimately, they have boosted up their confidence as continued their work in SMG this year.

SMGs in Achham

By RAP 3 on January 26, 2018

District:

Specific Maintenance Group (SMG) – piloting in its second year - is being implemented in Achham district in three DRCNs (69DR003, 69DR0011, 69DR018). All together 5 SMGs with 78 members (49% females) are working on these roads. Among these SMGs, Devkanya’B’ is being implemented at 69DR003  ( Kirthikham – Lungra – Chaurpati ) on an 8km road section (6+000 to 14+000). This newly formed group has completed over 20% of the estimated works within 20 days of its mobilisation. Remaining groups have also made similar progress in other roads. The picture shows gabion retaining wall constructed by Devkanya ‘B’ group at chainage 8+050.  DTA has planned to make advance payment (80% of completed works valuation) as per contract provision by the middle of next month. 

Quality control test at SMGs stone quarry site

By RAP 3 on January 11, 2018

District:

DTA Achham conducted quality control lab tests as well as verifying the stone quarry site for each of the five SMGs group on DRCN003, DRCN011 and DRCN018. A total of nine stone quarry sites were verified. DTA district lab conducted Specific Gravity and Water Absorption Tests at the each quarry and stone samples were taken to verify that these meet the specifications required. We are pleased to report that all nine quarries were found to meet the required specifications.

SMG orientation and refresher training

By RAP 3 on December 29, 2017

District:

DTA Achham conducted Orientation and refresher training to three Specific Maintenance Groups (SMGs). Orientation training for newly formed Devkanya(B) SMG was organised on 25th December 2017 and training to existing Kalika Devi and Devkanya SMGs was organised on 26th December 2017.  DTA team described on scope and procedures of SMG works focusing on workers and work site and how possible accidents can be reduced with the use of safety gears provided to them.  Procedures of construction of gabion wall, dry wall and stone soling was explained with the help of work method statement. Additionally, SMG groups were also informed about the payment procedure, Health and Insurance provision of RAP 3 provided to them.

Completion of second phase workshop

By RAP 3 on December 23, 2017

District:

DTA Achham along with program facilitators RTL Krishna Sharan Dhungana and DC Mahendra Shrestha have successfully completed the Second Phase Workshop on December 21, 2017 at DCC hall Mangalsen. 37 participants from Municipalities, Rural Municipalities, DCC/DTO representatives and District Engineers were present at the workshop. DCC chief Narbahadur Kunwar was the chairperson of the program. Krishna Sharan Dhungana discussed about the objectives of the second phase workshop along with recap of the first phase workshop and Mahendra Shrestha presented on Support Strategy for Federalization. The program ended with the vote of thanks from DCC chief and feedback from the Chairperson of the Sanfe Municipality and Vice Chairperson of the Vinayek Municipality.

SMG formation in Achham

By RAP 3 on December 14, 2017

District:

Chourpari Rural Municipality formed a new Specific Maintenance Group (SMG) for 69DR003 on 17th November 2017. Out of five SMGs projects this year, two of them still need to be formed. The meeting led by Chairperson of Chourpari Rural Municipality Mr. Harka Bahadur Saud successfully formed a new SMG at Lungra (ch 6+000 to 14+000) in-line with SMG guideline. RAP 3 DTAs (Jr. IoW and SLT) explained the guideline including the type of work to be done. Another group will be formed on 69DR018 shortly by Mangalsen Municipality to allow SMG works to be started from December.

 

Pages