Procurement

District:

S.N.

Name of Contract

Contract Period

Contract value without VAT

Total payment made to date

Remarks / Current Issues

From

To

Extended to

1

Dismantle and Construction of DDC building

26 Mar 2014

26 Aug 2014

 

410,000.00 (350,000 by RAP3, ASP and Nrs. 60,000.00 by DDC.)

327,754.81

Totsl PMNT including VAT Acc. actual IPC.

2

Construction of Toilet and Battery backup room

15 Dec 2014

15 Jan 2015

 

197,092.52

 

222,714.55

Final PMNT inc. VAT. (ASP H &S budget.)

3

Construction of DDC/DTO boundary wall

21 Apr. 2015

21 May 2015

 

352727.69

398530.14

Final PMNT Inc. VAT (ASP) budget.