Work Progress

District:

 

Ref. No.

Description

Start Date

End Date

Total Value Without VAT

Paid to Date

On target?

Key issues

1

Dismantle and construction of DCC building

26-Mar-14

26-Aug-14

                            410,000.00

        327,754.81

 Y

 

2

Constructionand of toilet and  Battery Back up room

15-Dec-14

15-Jan-15

                            197,092.50

        222,714.55

 Y

 

3

Constructionand of DDC DTO Boundary wall

21-Apr-15

21-May-15

                            352,727.69

        398,530.14

 Y

 

4

Solar System installation at Shreenagar RAP office

27-Jan-17

15-Mar-17

                            339,000.00

        339,000.00

 Y