Procurement

District:

DISTRICT CONTRACTS PROCURED

S. N.

Contract No.

Name of Contract

Contract Period

Contract value without VAT

Total payment made to date

Remarks / Current Issues

From

To

Extended to

 

YEAR 1 EMERGENCY MAINTENANCE

1

RAP3/2014/JHAPA/001

Pathariya-Gherabari temporary bamboo bridge construction

23 June.2014

9 July.2014

 

60,204.93

48,163.93

Completed

                          YEAR 1 SPECIFIC MAINTENANCE THROUGH CONTRACTORS

A.      BELOW 6M CONTRACT PACKAGES

1

DDC/JHAPA/RAP3/2014/GJ-011

Gauradaha-Maharanighoda-Swamichowk-Kowara-Juropani

03-Sep-14

31-Dec-14

30-Mar-15

436,539.90

 

On-going

2

DDC/JHAPA/RAP3/2014/KK-012

Kerkha-Kyampa-Sarangapada-Baigundhura

28-Dec-14

28-Feb-15

 

37,237.34

 

On-going

3

DDC/JHAPA/RAP3/2014/DP-013

Dharampur-Panchgachhi

28-Dec-14

28-Feb-15

 

90,591.90

 

On-going

4

DDC/JHAPA/RAP3/2014/CH-014

Charpane-Narayanchowk-Hattikila-Jayapur

18-Nov-14

31-Dec-14

30-Mar-15

229,384.92

 

On-going

5

DDC/JHAPA/RAP3/2014/SK-015

Sanischare-Khudunabari Road

03-Sep-14

31-Dec-14

30-Mar-15

0

 

On-going

6

DDC/JHAPA/RAP3/2014/GH-016

Garamani-Haldibari

08-Sep-14

31-Dec-14

 

24,478.00

 

On-going

7

DDC/JHAPA/RAP3/2014/SH-018

Sagaramatha-Haldibari-Goldhap-Chakchaki-Rajgadh

03-Sep-14

31-Dec-14

30-Mar-15

1,265,966.50

576,524.73

On-going

8

DDC/JHAPA/RAP3/2014/PG-019

Pathariya-Gherabari

03-Sep-14

31-Dec-14

30-Mar-15

292,468.70

 

On-going

B.       ABOVE 6M CONTRACT PACKAGES

9

DDC/JHAPA/RAP3/2014/GD-020

Ghailadubba-Dangibari-Chakchaki-Rajgadh

29-Aug-14

31-Dec-14

30-Mar-15

21,084.39

 

On-going

10

DDC/JHAPA/RAP3/2014/SG-021

Sainikmod-Goldhap-Dimakhutti-Rajgadh

29-Aug-14

31-Dec-14

30-Mar-15

1,274,170.36

 

On-going

11

DDC/JHAPA/RAP3/2014/BJ-022

Bhadrapur-Jyamirgadi-Dulabhari-Santinagar-Irautar

29-Aug-14

31-Dec-14

30-Mar-15

743,018.78

 

On-going

12

DDC/JHAPA/RAP3/2014/KB-023

Kakarvitta-Bahundangi

29-Aug-14

31-Dec-14

30-Mar-15

418,946.38

 

On-going

13

DDC/JHAPA/RAP3/2014/HP-024

Himali-Pathamari-Baniyani-Balubadi

29-Aug-14

31-Dec-14

30-Mar-15

82,602.90

 

On-going

YEAR 1 PERIODIC MAINTENANCE THROUGH CONTRACTORS

A.      BELOW 6M CONTRACT PACKAGES

1

DDC/JHAPA/RAP3/2014/GJ-011

Gauradaha-Maharanighoda-Swamichowk-Kowara-Juropani

03-Sep-14

31-Dec-14

30-Mar-15

2,461,520.00

 

On-going

2

DDC/JHAPA/RAP3/2014/KK-012

Kerkha-Kyampa-Sarangapada-Baigundhura

28-Dec-14

28-Feb-15

 

2,356,813.00

 

On-going

3

DDC/JHAPA/RAP3/2014/DP-013

Dharampur-Panchgachhi

28-Dec-14

28-Feb-15

 

2,176,636.88

 

On-going

4

DDC/JHAPA/RAP3/2014/CH-014

Charpane-Narayanchowk-Hattikila-Jayapur

18-Nov-14

31-Dec-14

30-Mar-15

2,907,120.00

 

On-going

5

DDC/JHAPA/RAP3/2014/SK-015

Sanischare-Khudunabari Road

03-Sep-14

31-Dec-14

30-Mar-15

3,524,260,00

 

On-going

6

DDC/JHAPA/RAP3/2014/GH-016

Garamani-Haldibari

08-Sep-14

31-Dec-14

 

2,580,700.00

 

On-going

7

DDC/JHAPA/RAP3/2014/SH-018

Sagaramatha-Haldibari-Goldhap-Chakchaki-Rajgadh

03-Sep-14

31-Dec-14

30-Mar-15

1,915,770.00

9,914.00

On-going

8

DDC/JHAPA/RAP3/2014/PG-019

Pathariya-Gherabari

03-Sep-14

31-Dec-14

30-Mar-15

2,121,360.00

 

On-going

B.       ABOVE 6M CONTRACT PACKAGES

9

DDC/JHAPA/RAP3/2014/GD-20

Ghailadubba-Dangibari-Chakchaki-Rajgadh

29-Aug-14

31-Dec-14

30-Mar-15

4,423,540.00

 

On-going

10

DDC/JHAPA/RAP3/2014/SG-21

Sainikmod-Goldhap-Dimakhutti-Rajgadh

29-Aug-14

31-Dec-14

30-Mar-15

6,097,250.00

4,829,363.00

On-going

11

DDC/JHAPA/RAP3/2014/BJ-022

Bhadrapur-Jyamirgadi-Dulabhari-Santinagar-Irautar

29-Aug-14

31-Dec-14

30-Mar-15

6,378,550.00

 

On-going

12

DDC/JHAPA/RAP3/2014/KB-023

Kakarvitta-Bahundangi

29-Aug-14

31-Dec-14

30-Mar-15

3,791,865.00

 

On-going

13

DDC/JHAPA/RAP3/2014/HP-024

Himali-Pathamari-Baniyani-Balubadi

29-Aug-14

31-Dec-14

30-Mar-15

4,757,818.50

 

On-going

YEAR 1 GOODS PROCUREMENT

1

DDC/JHA/GOODS/RAP3-2014/01

Construction tools

25 June.2014

15 July. 2014

3 Sept.2014

745,590.00

745,590.00

Completed

2

DDC/JHA/GOODS/RAP3-2014/02

Safety Gears

13.June 2014

3.July 2014

 

546,016.00

546,016.00

Completed

4

DDC/JHA/GOODS/RAP3-2015/01

Construction Tools

 

 

 

247,819.00

 

Under The procress of Agreement

5

DDC/JHA/GOODS/RAP3-2015/02

Safety Gears

 

 

 

77,560.00

 

Under The procress of Agreement

YEAR 1 RMG PACKAGES

1

RAP3/2014/JHA/RMG/GJ-01

Gauradah-Maharanijhoda-Kohabara-Juropani 1st Group

22-Aug-14

31 Jan .2015

-

213,136.67

108,078.07

Completed

2

RAP3/2014/JHA/RMG/GJ-02

Gauradah-Maharanijhoda-Kohabara-Juropani  2nd Group

21-Aug-14

31 Jan .2015

-

188,847.33

99,240.23

Completed

3

RAP3/2014/JHA/RMG/KK-03

Kerkha-Kyampa-Sarangpada-Baigundhura 1st Group

21-Aug-14

31 Jan .2015

-

210,625.00

121,982.37

Completed

4

RAP3/2014/JHA/RMG/KK-04

Kerkha-Kyampa-Sarangpada-Baigundhura 2nd Group

21-Aug-14

31 Jan .2015

-

158,040.00

89,657.56

Completed

5

RAP3/2014/JHA/RMG/DP-05

Dharampur-Panchgachhi 1st Group

24-Aug-14

31 Jan .2015

-

182,416.67

108,458.48

Completed

6

RAP3/2014/JHA/RMG/DP-06

Dharampur-Panchgachhi 2nd Group

18-Aug-14

31 Jan .2015

-

132,979.50

81,531.98

Completed

7

RAP3/2014/JHA/RMG/SL-07

Satashidham-Kailashdham-Larumba

25-Aug-14

31 Jan .2015

-

78,491.67

43,035.25

Completed

8

RAP3/2014/JHA/RMG/GD-08

Gailadubba-Dangibari-Chakchaki-Rajgad 1st Group

17-Aug-14

31 Jan .2015

-

160,877.50

94,732.86

Completed

9

RAP3/2014/JHA/RMG/GD-09

Gailadubba-Dangibari-Chakchaki-Rajgad 2nd Group

23-Aug-14

31 Jan .2015

-

160,877.50

83,275.99

Completed

10

RAP3/2014/JHA/RMG/CH-10

Charpane-Narayanchowk-Hatikilla-Jaypur 1st Group

21-Aug-14

31 Jan .2015

-

106,999.17

56,785.56

Completed

11

RAP3/2014/JHA/RMG/CH-11

Charpane-Narayanchowk-Hatikilla-Jaypur  2nd  Group

22-Aug-14

31 Jan .2015

-

106,999.17

63,692.62

Completed

12

RAP3/2014/JHA/RMG/SG-12

Sainikmod-Gooldhap-Dimakoti-Rajgad 1st Group

20-Aug-14

31 Jan .2015

-

138,093.33

74,282.73

Completed

13

RAP3/2014/JHA/RMG/SG-13

Sainikmod-Gooldhap-Dimakoti-Rajgad 2nd Group

23-Aug-14

31 Jan .2015

-

160,522.58

69,868.03

Completed

14

RAP3/2014/JHA/RMG/SK-14

Sanishchare-Khudunabari

24-Aug-14

31 Jan .2015

-

133,615.00

68,285.44

Completed

15

RAP3/2014/JHA/RMG/GH-15

Garamani-Haldibari

20-Aug-14

31 Jan. 2015

-

106,716.67

56,802.41

Completed

16

RAP3/2014/JHA/RMG/BJ-16

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar 1st Group

21-Aug-14

31 Jan .2015

-

160,368.33

69,627.48

Completed

17

RAP3/2014/JHA/RMG/BJ-17

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar  2nd Group

22-Aug-14

31 Jan .2015

-

241,646.67

159,583.80

Completed

18

RAP3/2014/JHA/RMG/BJ-18

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar 3rd Group

22-Aug-14

31 Jan .2015

-

231,904.00

137,074.30

Completed

19

RAP3/2014/JHA/RMG/IN-19

Itabhatta-Bhrikuti-Nindasiran 1st Group

22-Aug-14

31 Jan .2015

-

161,063.33

112,090.72

Completed

20

RAP3/2014/JHA/RMG/IN-20

Itabhatta-Bhrikuti-Nindasiran 1st Group

22-Aug-14

31 Jan .2015

-

222,592.83

141,557.91

Completed

21

RAP3/2014/JHA/RMG/KB-21

Kakarvitta-Bahundangi 1st Group

22-Aug-14

31 Jan .2015

 

211,110.00

79,427.41

Completed

22

RAP3/2014/JHA/RMG/KB-22

Kakarvitta-Bahundangi  2nd  Group

22-Aug-14

31 Jan .2015

-

183,100.50

121,985.95

Completed

23

RAP3/2014/JHA/RMG/SH-23

Sagarmatha-Haldibari-Chakchaki-Rajgad 1st Group

21-Aug-14

31 Jan .2015

-

187,954.17

126,240.01

Completed

24

RAP3/2014/JHA/RMG/SH-24

Sagarmatha-Haldibari-Chakchaki-Rajgad 2nd Group

23-Aug-14

31 Jan .2015

-

163,092.50

87,160.99

Completed

25

RAP3/2014/JHA/RMG/HP-25

Himali-Pathamari-Banyani-Balubadi

2 Sept.t 2014

31 Jan .2015

-

169,226.50

61,457.18

Completed

26

RAP3/2014/JHA/RMG/PG-26

Pathriya-Gherabari

21-Aug-14

31 Jan .2015

-

134,767.37

93,663.37

Completed

YEAR 2 RMG PACKAGES

1

RAP3/2015/JHP/RMG/GJ-01

Gauradah-Maharanijhoda-Kohabara-Juropani 1st Group

1 Feb. 2015

30 Sept. .2015

-

245,573.33

24,744.40

On going

2

RAP3/2015/JHP/RMG/GJ-02

Gauradah-Maharanijhoda-Kohabara-Juropani  2nd Group

1 Feb. 2015

30 Sept. .2015

-

227,258.67

17,876.40

On going

3

RAP3/2015/JHP/RMG/KK-03

Kerkha-Kyampa-Sarangpada-Baigundhura 1st Group

1 Feb. 2015

30 Sept. .2015

-

242,280.00

29,140.33

On going

4

RAP3/2015/JHP/RMG/KK-04

Kerkha-Kyampa-Sarangpada-Baigundhura 2nd Group

1 Feb. 2015

30 Sept. .2015

-

173,600.00

24,332.73

On going

5

RAP3/20145JHP/RMG/DP-05

Dharampur-Panchgachhi 1st Group

1 Feb. 2015

30 Sept. .2015

-

195,973.33

20,833.73

On going

6

RAP3/2015/JHP/RMG/DP-06

Dharampur-Panchgachhi 2nd Group

1 Feb. 2015

30 Sept. .2015

-

152,476.00

15,339.33

On going

7

RAP3/2015/JHP/RMG/DS-07

Dudhe-Shivganja-Panchgachhi-Mahabhara-Korobari 1st Group

-

-

-

206,726.67

-

Under The procress of Agreement

8

RAP3/2015/JHP/RMG/DS-08

Dudhe-Shivganja-Panchgachhi-Mahabhara-Korobari 2st Group

-

-

-

241,066.67

-

Under The procress of Agreement

9

RAP3/2015/JHP/RMG/SL-09

Satashidham-Kailashdham-Larumba

1 Feb. 2015

30 Sept. .2015

-

79,773.33

9,628.27

On going

10

RAP3/2015/JHP/RMG/SS-10

Surunga-Sarnamati-Taghandubba-Kumarkhod 1st Group

-

-

 

332,466.67

-

Under The procress of Agreement

11

RAP3/2015/JHP/RMG/SS-11

Surunga-Sarnamati-Taghandubba-Kumarkhod 1st Group

-

-

 

240,893.33

-

Under The procress of Agreement

12

RAP3/2015/JHP-/RMG/GD-12

Gailadubba-Dangibari-Chakchaki-Rajgad 1st Group

1 Feb. 2015

30 Sept. .2015

-

206,380.00

15,896.13

On going

13

RAP3/2015/JHP/RMG/GD-13

Gailadubba-Dangibari-Chakchaki-Rajgad 2nd Group

1 Feb. 2015

30 Sept. .2015

-

206,380.00

24,137.73

On going

14

RAP3/2015/JHP/RMG/CH-14

Charpane-Narayanchowk-Hatikilla-Jaypur 1st Group

1 Feb. 2015

30 Sept. .2015

-

136,313.33

14,692.60

On going

15

RAP3/2015/JHP/RMG/CH-15

Charpane-Narayanchowk-Hatikilla-Jaypur  2nd  Group

1 Feb. 2015

30 Sept. .2015

-

136,313.33

10,571.80

On going

16

RAP3/2015/JHP/RMG/SG-16

Sainikmod-Gooldhap-Dimakoti-Rajgad 1st Group

1 Feb. 2015

30 Sept. .2015

-

195,626.67

19,416.80

On going

17

RAP3/2015/JHP/RMG/SG-17

Sainikmod-Gooldhap-Dimakoti-Rajgad 2nd Group

1 Feb. 2015

30 Sept. .2015

-

199,060.67

15,296.00

On going

18

RAP3/2015/JHP/RMG/SK-18

Sanishchare-Khudunabari

1 Feb. 2015

30 Sept. .2015

-

171,000.00

16,452.93

On going

19

RAP3/2015/JHP/RMG/GH-19

Garamani-Haldibari

1 Feb. 2015

30 Sept. .2015

-

146,373.33

12,458.87

On going

20

RAP3/2015/JHP/RMG/BJ-20

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar 1st Group

1 Feb. 2015

30 Sept. .2015

-

215,746.67

14,949.33

On going

21

RAP3/2015/JHP/RMG/BJ-21

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar  2nd Group

1 Feb. 2015

30 Sept. .2015

-

331,253.33

32,249.33

On going

22

RAP3/2015/JHP/RMG/BJ-22

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar 3rd Group

1 Feb. 2015

30 Sept. .2015

-

245,472.00

23,472.60

On going

23

RAP3/2015/JHP/RMG/IN-23

Itabhatta-Bhrikuti-Nindasiran 1st Group

1 Feb. 2015

30 Sept. .2015

-

196,666.67

22,294.00

On going

24

RAP3/2015/JHP/RMG/IN-24

Itabhatta-Bhrikuti-Nindasiran 1st Group

1 Feb. 2015

30 Sept. .2015

-

244,742.67

23,667.60

On going

25

RAP3/2015/JHP/RMG/KB-25

Kakarvitta-Bahundangi 1st Group

1 Feb. 2015

30 Sept. .2015

 

242,800.00

16,842.93

On going

26

RAP3/2015/JHP/RMG/KB-26

Kakarvitta-Bahundangi  2nd  Group

1 Feb. 2015

30 Sept. .2015

-

194,724.00

20,963.73

On going

27

RAP3/2015/JHP/RMG/SH-27

Sagarmatha-Haldibari-Chakchaki-Rajgad 1st Group

1 Feb. 2015

30 Sept. .2015

-

251,473.33

25,424.67

On going

28

RAP3/2015/JHP/RMG/SH-28

Sagarmatha-Haldibari-Chakchaki-Rajgad 2nd Group

1 Feb. 2015

30 Sept. .2015

-

228,580.00

16,839.67

On going

29

RAP3/2015/JHP/RMG/HP-29

Himali-Pathamari-Banyani-Balubadi

1 Feb. 2015

30 Sept. .2015

-

278,772.00

16,131.20

On going

30

RAP3/2015/JHP/RMG/PG-30

Pathriya-Gherabari

1 Feb. 2015

30 Sept. .2015

-

177,818.93

20,338.67

On going

Procurement

District:

DISTRICT CONTRACTS PROCURED

SN

Contract No.

Name of Contract

Contract Period

Contract value without VAT

Total payment made to date

Remarks / Current Issues

From

To

Extended to

 

YEAR 1 EMERGENCY MAINTENANCE

1

RAP3/2014/JHAPA/001

Pathariya-Gherabari temporary bamboo bridge construction

23 June 2014

9 July 2014

 

60,204.93

48,163.93

Completed

                          YEAR 1 SPECIFIC MAINTENANCE THROUGH CONTRACTORS

A.      BELOW 6M CONTRACT PACKAGES

1

DDC/JHAPA/RAP3/2014/GJ-011

Gauradaha-Maharanighoda-Swamichowk-Kowara-Juropani

03-Sep-14

31-Dec-14

30-Mar-15

436,539.90

 

On-going

2

DDC/JHAPA/RAP3/2014/KK-012

Kerkha-Kyampa-Sarangapada-Baigundhura

28-Dec-14

28-Feb-15

 

37,237.34

 

On-going

3

DDC/JHAPA/RAP3/2014/DP-013

Dharampur-Panchgachhi

28-Dec-14

28-Feb-15

 

90,591.90

 

On-going

4

DDC/JHAPA/RAP3/2014/CH-014

Charpane-Narayanchowk-Hattikila-Jayapur

18-Nov-14

31-Dec-14

30-Mar-15

229,384.92

 

On-going

5

DDC/JHAPA/RAP3/2014/SK-015

Sanischare-Khudunabari Road

03-Sep-14

31-Dec-14

30-Mar-15

0

 

On-going

6

DDC/JHAPA/RAP3/2014/GH-016

Garamani-Haldibari

08-Sep-14

31-Dec-14

 

24,478.00

 

On-going

7

DDC/JHAPA/RAP3/2014/SH-018

Sagaramatha-Haldibari-Goldhap-Chakchaki-Rajgadh

03-Sep-14

31-Dec-14

30-Mar-15

1,265,966.50

576,524.73

On-going

8

DDC/JHAPA/RAP3/2014/PG-019

Pathariya-Gherabari

03-Sep-14

31-Dec-14

30-Mar-15

292,468.70

 

On-going

B.       ABOVE 6M CONTRACT PACKAGES

9

DDC/JHAPA/RAP3/2014/GD-020

Ghailadubba-Dangibari-Chakchaki-Rajgadh

29-Aug-14

31-Dec-14

30-Mar-15

21,084.39

 

On-going

10

DDC/JHAPA/RAP3/2014/SG-021

Sainikmod-Goldhap-Dimakhutti-Rajgadh

29-Aug-14

31-Dec-14

30-Mar-15

1,274,170.36

 

On-going

11

DDC/JHAPA/RAP3/2014/BJ-022

Bhadrapur-Jyamirgadi-Dulabhari-Santinagar-Irautar

29-Aug-14

31-Dec-14

30-Mar-15

743,018.78

 

On-going

12

DDC/JHAPA/RAP3/2014/KB-023

Kakarvitta-Bahundangi

29-Aug-14

31-Dec-14

30-Mar-15

418,946.38

 

On-going

13

DDC/JHAPA/RAP3/2014/HP-024

Himali-Pathamari-Baniyani-Balubadi

29-Aug-14

31-Dec-14

30-Mar-15

82,602.90

 

On-going

YEAR 1 PERIODIC MAINTENANCE THROUGH CONTRACTORS

A.      BELOW 6M CONTRACT PACKAGES

1

DDC/JHAPA/RAP3/2014/GJ-011

Gauradaha-Maharanighoda-Swamichowk-Kowara-Juropani

03-Sep-14

31-Dec-14

30-Mar-15

2,461,520.00

 

On-going

2

DDC/JHAPA/RAP3/2014/KK-012

Kerkha-Kyampa-Sarangapada-Baigundhura

28-Dec-14

28-Feb-15

 

2,356,813.00

 

On-going

3

DDC/JHAPA/RAP3/2014/DP-013

Dharampur-Panchgachhi

28-Dec-14

28-Feb-15

 

2,176,636.88

 

On-going

4

DDC/JHAPA/RAP3/2014/CH-014

Charpane-Narayanchowk-Hattikila-Jayapur

18-Nov-14

31-Dec-14

30-Mar-15

2,907,120.00

 

On-going

5

DDC/JHAPA/RAP3/2014/SK-015

Sanischare-Khudunabari Road

03-Sep-14

31-Dec-14

30-Mar-15

3,524,260,00

 

On-going

6

DDC/JHAPA/RAP3/2014/GH-016

Garamani-Haldibari

08-Sep-14

31-Dec-14

 

2,580,700.00

 

On-going

7

DDC/JHAPA/RAP3/2014/SH-018

Sagaramatha-Haldibari-Goldhap-Chakchaki-Rajgadh

03-Sep-14

31-Dec-14

30-Mar-15

1,915,770.00

9,914.00

On-going

8

DDC/JHAPA/RAP3/2014/PG-019

Pathariya-Gherabari

03-Sep-14

31-Dec-14

30-Mar-15

2,121,360.00

 

On-going

B.       ABOVE 6M CONTRACT PACKAGES

9

DDC/JHAPA/RAP3/2014/GD-20

Ghailadubba-Dangibari-Chakchaki-Rajgadh

29-Aug-14

31-Dec-14

30-Mar-15

4,423,540.00

 

On-going

10

DDC/JHAPA/RAP3/2014/SG-21

Sainikmod-Goldhap-Dimakhutti-Rajgadh

29-Aug-14

31-Dec-14

30-Mar-15

6,097,250.00

4,829,363.00

On-going

11

DDC/JHAPA/RAP3/2014/BJ-022

Bhadrapur-Jyamirgadi-Dulabhari-Santinagar-Irautar

29-Aug-14

31-Dec-14

30-Mar-15

6,378,550.00

 

On-going

12

DDC/JHAPA/RAP3/2014/KB-023

Kakarvitta-Bahundangi

29-Aug-14

31-Dec-14

30-Mar-15

3,791,865.00

 

On-going

13

DDC/JHAPA/RAP3/2014/HP-024

Himali-Pathamari-Baniyani-Balubadi

29-Aug-14

31-Dec-14

30-Mar-15

4,757,818.50

 

On-going

YEAR 1 GOODS PROCUREMENT

1

DDC/JHA/GOODS/RAP3-2014/01

Construction tools

25 June 2014

15 July 2014

3 Sept 2014

745,590.00

745,590.00

Completed

2

DDC/JHA/GOODS/RAP3-2014/02

Safety Gears

13 June 2014

3 July 2014

 

546,016.00

546,016.00

Completed

4

DDC/JHA/GOODS/RAP3-2015/01

Construction Tools

 

 

 

247,819.00

 

Under The procress of Agreement

5

DDC/JHA/GOODS/RAP3-2015/02

Safety Gears

 

 

 

77,560.00

 

Under The procress of Agreement

YEAR 1 RMG PACKAGES

1

RAP3/2014/JHA/RMG/GJ-01

Gauradah-Maharanijhoda-Kohabara-Juropani 1st Group

22-Aug-14

31 Jan 2015

-

213,136.67

108,078.07

Completed

2

RAP3/2014/JHA/RMG/GJ-02

Gauradah-Maharanijhoda-Kohabara-Juropani  2nd Group

21-Aug-14

31 Jan 2015

-

188,847.33

99,240.23

Completed

3

RAP3/2014/JHA/RMG/KK-03

Kerkha-Kyampa-Sarangpada-Baigundhura 1st Group

21-Aug-14

31 Jan 2015

-

210,625.00

121,982.37

Completed

4

RAP3/2014/JHA/RMG/KK-04

Kerkha-Kyampa-Sarangpada-Baigundhura 2nd Group

21-Aug-14

31 Jan .2015

-

158,040.00

89,657.56

Completed

5

RAP3/2014/JHA/RMG/DP-05

Dharampur-Panchgachhi 1st Group

24-Aug-14

31 Jan 2015

-

182,416.67

108,458.48

Completed

6

RAP3/2014/JHA/RMG/DP-06

Dharampur-Panchgachhi 2nd Group

18-Aug-14

31 Jan 2015

-

132,979.50

81,531.98

Completed

7

RAP3/2014/JHA/RMG/SL-07

Satashidham-Kailashdham-Larumba

25-Aug-14

31 Jan 2015

-

78,491.67

43,035.25

Completed

8

RAP3/2014/JHA/RMG/GD-08

Gailadubba-Dangibari-Chakchaki-Rajgad 1st Group

17-Aug-14

31 Jan 2015

-

160,877.50

94,732.86

Completed

9

RAP3/2014/JHA/RMG/GD-09

Gailadubba-Dangibari-Chakchaki-Rajgad 2nd Group

23-Aug-14

31 Jan .2015

-

160,877.50

83,275.99

Completed

10

RAP3/2014/JHA/RMG/CH-10

Charpane-Narayanchowk-Hatikilla-Jaypur 1st Group

21-Aug-14

31 Jan 2015

-

106,999.17

56,785.56

Completed

11

RAP3/2014/JHA/RMG/CH-11

Charpane-Narayanchowk-Hatikilla-Jaypur  2nd  Group

22-Aug-14

31 Jan 2015

-

106,999.17

63,692.62

Completed

12

RAP3/2014/JHA/RMG/SG-12

Sainikmod-Gooldhap-Dimakoti-Rajgad 1st Group

20-Aug-14

31 Jan 2015

-

138,093.33

74,282.73

Completed

13

RAP3/2014/JHA/RMG/SG-13

Sainikmod-Gooldhap-Dimakoti-Rajgad 2nd Group

23-Aug-14

31 Jan 2015

-

160,522.58

69,868.03

Completed

14

RAP3/2014/JHA/RMG/SK-14

Sanishchare-Khudunabari

24-Aug-14

31 Jan 2015

-

133,615.00

68,285.44

Completed

15

RAP3/2014/JHA/RMG/GH-15

Garamani-Haldibari

20-Aug-14

31 Jan 2015

-

106,716.67

56,802.41

Completed

16

RAP3/2014/JHA/RMG/BJ-16

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar 1st Group

21-Aug-14

31 Jan .2015

-

160,368.33

69,627.48

Completed

17

RAP3/2014/JHA/RMG/BJ-17

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar  2nd Group

22-Aug-14

31 Jan 2015

-

241,646.67

159,583.80

Completed

18

RAP3/2014/JHA/RMG/BJ-18

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar 3rd Group

22-Aug-14

31 Jan 2015

-

231,904.00

137,074.30

Completed

19

RAP3/2014/JHA/RMG/IN-19

Itabhatta-Bhrikuti-Nindasiran 1st Group

22-Aug-14

31 Jan 2015

-

161,063.33

112,090.72

Completed

20

RAP3/2014/JHA/RMG/IN-20

Itabhatta-Bhrikuti-Nindasiran 1st Group

22-Aug-14

31 Jan 2015

-

222,592.83

141,557.91

Completed

21

RAP3/2014/JHA/RMG/KB-21

Kakarvitta-Bahundangi 1st Group

22-Aug-14

31 Jan .2015

 

211,110.00

79,427.41

Completed

22

RAP3/2014/JHA/RMG/KB-22

Kakarvitta-Bahundangi  2nd  Group

22-Aug-14

31 Jan 2015

-

183,100.50

121,985.95

Completed

23

RAP3/2014/JHA/RMG/SH-23

Sagarmatha-Haldibari-Chakchaki-Rajgad 1st Group

21-Aug-14

31 Jan 2015

-

187,954.17

126,240.01

Completed

24

RAP3/2014/JHA/RMG/SH-24

Sagarmatha-Haldibari-Chakchaki-Rajgad 2nd Group

23-Aug-14

31 Jan 2015

-

163,092.50

87,160.99

Completed

25

RAP3/2014/JHA/RMG/HP-25

Himali-Pathamari-Banyani-Balubadi

2 Sept 2014

31 Jan 2015

-

169,226.50

61,457.18

Completed

26

RAP3/2014/JHA/RMG/PG-26

Pathriya-Gherabari

21-Aug-14

31 Jan 2015

-

134,767.37

93,663.37

Completed

YEAR 2 RMG PACKAGES

1

RAP3/2015/JHP/RMG/GJ-01

Gauradah-Maharanijhoda-Kohabara-Juropani 1st Group

1 Feb 2015

30 Sept 2015

-

245,573.33

24,744.40

On going

2

RAP3/2015/JHP/RMG/GJ-02

Gauradah-Maharanijhoda-Kohabara-Juropani  2nd Group

1 Feb 2015

30 Sept 2015

-

227,258.67

17,876.40

On going

3

RAP3/2015/JHP/RMG/KK-03

Kerkha-Kyampa-Sarangpada-Baigundhura 1st Group

1 Feb 2015

30 Sept 2015

-

242,280.00

29,140.33

On going

4

RAP3/2015/JHP/RMG/KK-04

Kerkha-Kyampa-Sarangpada-Baigundhura 2nd Group

1 Feb 2015

30 Sept 2015

-

173,600.00

24,332.73

On going

5

RAP3/20145JHP/RMG/DP-05

Dharampur-Panchgachhi 1st Group

1 Feb 2015

30 Sept 2015

-

195,973.33

20,833.73

On going

6

RAP3/2015/JHP/RMG/DP-06

Dharampur-Panchgachhi 2nd Group

1 Feb 2015

30 Sept 2015

-

152,476.00

15,339.33

On going

7

RAP3/2015/JHP/RMG/DS-07

Dudhe-Shivganja-Panchgachhi-Mahabhara-Korobari 1st Group

-

-

-

206,726.67

-

Under The procress of Agreement

8

RAP3/2015/JHP/RMG/DS-08

Dudhe-Shivganja-Panchgachhi-Mahabhara-Korobari 2st Group

-

-

-

241,066.67

-

Under The procress of Agreement

9

RAP3/2015/JHP/RMG/SL-09

Satashidham-Kailashdham-Larumba

1 Feb 2015

30 Sept 2015

-

79,773.33

9,628.27

On going

10

RAP3/2015/JHP/RMG/SS-10

Surunga-Sarnamati-Taghandubba-Kumarkhod 1st Group

-

-

 

332,466.67

-

Under The procress of Agreement

11

RAP3/2015/JHP/RMG/SS-11

Surunga-Sarnamati-Taghandubba-Kumarkhod 1st Group

-

-

 

240,893.33

-

Under The procress of Agreement

12

RAP3/2015/JHP-/RMG/GD-12

Gailadubba-Dangibari-Chakchaki-Rajgad 1st Group

1 Feb 2015

30 Sept 2015

-

206,380.00

15,896.13

On going

13

RAP3/2015/JHP/RMG/GD-13

Gailadubba-Dangibari-Chakchaki-Rajgad 2nd Group

1 Feb 2015

30 Sept 2015

-

206,380.00

24,137.73

On going

14

RAP3/2015/JHP/RMG/CH-14

Charpane-Narayanchowk-Hatikilla-Jaypur 1st Group

1 Feb 2015

30 Sept 2015

-

136,313.33

14,692.60

On going

15

RAP3/2015/JHP/RMG/CH-15

Charpane-Narayanchowk-Hatikilla-Jaypur  2nd  Group

1 Feb 2015

30 Sept 2015

-

136,313.33

10,571.80

On going

16

RAP3/2015/JHP/RMG/SG-16

Sainikmod-Gooldhap-Dimakoti-Rajgad 1st Group

1 Feb 2015

30 Sept 2015

-

195,626.67

19,416.80

On going

17

RAP3/2015/JHP/RMG/SG-17

Sainikmod-Gooldhap-Dimakoti-Rajgad 2nd Group

1 Feb 2015

30 Sept 2015

-

199,060.67

15,296.00

On going

18

RAP3/2015/JHP/RMG/SK-18

Sanishchare-Khudunabari

1 Feb 2015

30 Sept 2015

-

171,000.00

16,452.93

On going

19

RAP3/2015/JHP/RMG/GH-19

Garamani-Haldibari

1 Feb 2015

30 Sept 2015

-

146,373.33

12,458.87

On going

20

RAP3/2015/JHP/RMG/BJ-20

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar 1st Group

1 Feb 2015

30 Sept 2015

-

215,746.67

14,949.33

On going

21

RAP3/2015/JHP/RMG/BJ-21

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar  2nd Group

1 Feb 2015

30 Sept 2015

-

331,253.33

32,249.33

On going

22

RAP3/2015/JHP/RMG/BJ-22

Bhadrapur-Jyamirgadi-Dhulabari-Shantinagar-Irautar 3rd Group

1 Feb 2015

30 Sept 2015

-

245,472.00

23,472.60

On going

23

RAP3/2015/JHP/RMG/IN-23

Itabhatta-Bhrikuti-Nindasiran 1st Group

1 Feb 2015

30 Sept 2015

-

196,666.67

22,294.00

On going

24

RAP3/2015/JHP/RMG/IN-24

Itabhatta-Bhrikuti-Nindasiran 1st Group

1 Feb 2015

30 Sept 2015

-

244,742.67

23,667.60

On going

25

RAP3/2015/JHP/RMG/KB-25

Kakarvitta-Bahundangi 1st Group

1 Feb 2015

30 Sept 2015

 

242,800.00

16,842.93

On going

26

RAP3/2015/JHP/RMG/KB-26

Kakarvitta-Bahundangi  2nd  Group

1 Feb 2015

30 Sept 2015

-

194,724.00

20,963.73

On going

27

RAP3/2015/JHP/RMG/SH-27

Sagarmatha-Haldibari-Chakchaki-Rajgad 1st Group

1 Feb 2015

30 Sept 2015

-

251,473.33

25,424.67

On going

28

RAP3/2015/JHP/RMG/SH-28

Sagarmatha-Haldibari-Chakchaki-Rajgad 2nd Group

1 Feb 2015

30 Sept 2015

-

228,580.00

16,839.67

On going

29

RAP3/2015/JHP/RMG/HP-29

Himali-Pathamari-Banyani-Balubadi

1 Feb 2015

30 Sept 2015

-

278,772.00

16,131.20

On going

30

RAP3/2015/JHP/RMG/PG-30

Pathriya-Gherabari

1 Feb 2015

30 Sept 2015

-

177,818.93

20,338.67

On going