Work Progress

District:

SUMMARY SHEET OF ALL CONTRACT

Ref

Brief Description

Type

Location

Start date

End date

Total Value (NRs.) (inc. VAT)

Paid to date (NRs.)

On target? (Y/N)

Key issues or actions required

DDC/MOR/RAP3/NCB-21

 Maintainance of Kanepokhari-Letang-Warangi-Budhabare Road (05DR020)

Works

 

12-Sep-14

25 Jan 015

6,008,321.64

4,226,564.99

 

 

DDC/MOR/RAP3/NCB-22

Maintainance of Kerabari-Patigaun-Dandabazar Road (05DR007)

Works

 

24-Sep-14

25 Jan 015

6,339,683.97

5,007,073.56

 

 

DDC/MOR/RAP3/NCB-23

Maintainance of Khorsane-Kerabari-Singhdevi-Samewa Road (05DR008)

Works

 

24-Jun-14

25 Jan 015

6,811,736.72

4,506,754.59

 

 

DDC/MOR/RAP3/NCB-24

Maintainance of Nimuwa -Hattimuda-Sisbani Badhara Road and Kaseni-Banigama Dangraha Road (05DR003 & 05DR009)

Works

 

24-Jun-14

15 Feb 015

7,928,545.54

6,463,312.95

 

 

DDC/MOR/RAP3/NCB-25

Maintainance of Belbari-Lokhara-Bhogateni-Aaitabare Road (05DR017)

Works

 

12-Sep-14

25 Jan 015

9,153,873.40

6,137,665.62

 

 

DDC/MOR/RAP3/NCB-26

Maintainance of Rani-Budhanagar-Tarigama Road (05DR006)

Works

 

18-Jun-14

25 Jan 015

4,742,242.07

4,652,501.10

 

 

DDC/MOR/RAP3/SQ-27

Maintainance of Sisbani-Jahada-Ramchowk Road (05DR015)

Works

 

19-May

25 Jan 015

1,433,383.35

1,302,047.25

 

 

DDC/MOR/RAP3/SQ-28

Maintainance of Milanchowk-Lakhantari Road (05DR004)

Works

 

21-May-14

25 Jan 015

989,531.26

844,015.56

 

 

DDC/MOR/RAP3/SQ-29

Maintainance of Kadamaha-Nocha Boarder Road (05DR016)

Works

 

20-May-14

25 Jan 015

1,324,622.95

1,192,087.95

 

 

DDC/MOR/RAP3/NCB-30

Maintainance of Sundarpur-Yangshila-Dharan Road (05DR001)

Works

 

13-Oct-14

30 Jan 015

9,227,871.82

9,166,856.63

 

 

DDC/MOR/RAP3/NCB-31

Maintainance of Kishanchowk-Tadi-Ramite-Miklajung Road (05DR026)

Works

 

12-Sep-14

31 Jan 015

6,705,726.88

1,185,554.00

 

 

DDC/MOR/RAP3/NCB-32

Maintainance of Katahari-Lakshaminiya-Pokhariya-Nocha-Amahi (Boarder) Road (05DR014)

Works

 

28-Jun-14

12 Feb 015

3,827,651.56

3,821,397.00

 

 

DDC/MOR/RAP3/NCB-33

Maintainance of Pathari-Jante Road (05DR021)

Works

 

25-Sep-14

25 Jan 015

1,605,031.52

1,599,381.52

 

 

DDC/MOR/RAP3/NCB-34

Maintainance of Jhapadtal-Bardanga Road (05DR025)

Works

 

14-Jul-14

15 Feb 015

3,642,848.29

3,312,184.24

 

 

DDC/MOR/RAP3/NCB-35

Maintainance of Kadupada-Sijuwa-Jhurkiya Boarder Road (05DR027)

Works

 

14-Jul-14

25 Jan 015

4,276,368.59

3,963,004.32

 

 

DDC/MOR/RAP3/NCB-36

Maintainance of Mahadeva-Chaukighat Road (05DR028)

Works

 

22-Aug-14

25 Jan 015

3,319,373.24

3,275,805.76

 

 

DDC/MOR/RAP3/NCB-41

Maintainance of Bhaunna-Aamtola Road (05DR018)

Works

 

12-Sep-14

25 Jan 015

6,261,596.67

4,948,843.76

 

 

DDC/MOR/RAP3/SQ-42

Maintainance of Gobindapur-Larikatta Road (05DR024)

Works

 

25-Oct-14

25 Jan 015

1,982,784.45

1,971,149.40

 

 

DDC/MOR/RAP3/SQ-43

Maintainance of Bhaudaha Nayabazar Road (05DR012)

Works

 

13-Oct-14

25 Jan 015

1,770,820.18

1,696,495.56

 

 

DDC/MOR/RAP3/SQ-44

Maintainance of Nayabazar Thalah Road (05DR013)

Works

 

26-Jun-14

25 Jan 015

1,885,661.51

1,538,564.99

 

 

DDC/MOR/RAP3/SQ-45

Maintainance of Aamgachhi-Takuwa Road (05DR023)

Works

 

13-Oct-14

25 Jan 015

1,933,226.60

1,902,263.20

 

 

DDC/MOR/RAP3/SQ-46

Maintainance of Pidarmani-Sidraha Road (05DR011)

Works

 

11-Jul-14

25 Jan 015

1,761,569.06

1,729,943.08

 

 

Total

92,932,471.27

74,443,467.03