Trimester Report: November 2016 - March 2017

Publish Date: 
April, 2017
Author: 
RAP 3

This report covers the progress of RAP3 over the second Trimester of FY 2073-74, 16th November 2016 to 15th March 2017. It provides data and information relating to progress of RAP3 over the last Trimester.

A Summary reviews the physical and financial progress of RAP at the end of the last Trimester. This shows cumulative physical progress in relation to the programme extended period i.e. June 2019. The programme physical progress has reached at 73.3%, time elapsed at 62.79% and financial progress at 66.12%, all nicely grouped. The summary also lists activities carried out last Trimester and those planned for the next Trimester.