Back to top

RAP3 MHLR

Monthly PMR – June 2021

  • Design drawings and reports of all 4 bridges complete. Independent Checker reviewing these for finalising.
  • 0.48km substantial completion achieved on MHLR construction this month taking the total to 48.41 km.
  • L-section drawing of Chankheli - Saththaple section complete.
  • Healthy workforce team organised 27 orientations on first aid kit management, risk reduction, Covid 19 prevention, nutrition, personal and menstrual hygiene for S/RBGs in MHLR, and family planning and child vaccination, where 382 members, including 100 women, benefitted.
  • Bioengineering works started in different locations along MHLR

Monthly PMR – May 2021

  • Detailed design, drawing and report of Luma Bridge submitted by Contractor incorporating our comments. Independent Checker’s review remaining. Internal review of designs of Darke and Lebra Khola bridge ongoing. Detailed design of Melchham Khola bridge expected this week.   
  • 2.5 km substantial completion achieved on MHLR construction this month taking the total to 48 km.
  • Healthy workforce team organised 14 orientations on first aid kit management, risk reduction, Covid 19 prevention, nutrition and personal hygiene for S/RBGs in MHLR and family planning and child vaccination, where 256 members, including 53 women, benefitted.

Monthly PMR – April 2021

  • Conceptual designs for bridges now finalised.  Detailed designs for Luma and Darke submitted by Contractor.
  • 2 km substantial completion achieved on MHLR this month taking the total to 45.2 km.
  • Healthy workforce team conducted 4 outreach clinics in Mugu and Humla examining and providing medicines to 49 workers including 23 women.
  • Organised 13 events of orientations on first aid kit management, risk reduction and Covid 19 prevention, nutrition and personal hygiene for S/RBGs in MHLR, where 308 members, including 66 women, benefitted.  

Monthly PMR – March 2021

  • Lab testing of soil samples from river crossing sites ongoing. Conceptual design drawings submitted by contractor reviewed and comments shared.
  • Completed 63km length of full width (4.5m) track opening. Substantially completed 2 km this month taking the total to 43.2 km length.
  • Healthy workforce team conducted 4 outreach clinics in Mugu and Humla examining and provided medicines to 47 workers including 18 women.
  • Organised 54 orientations on first aid kit management, risk reduction and Covid 19 prevention, for S/RBGs in MHLR, where 798 members, including 192 women, benefitted.  

Monthly PMR – February 2021

  • Drill holes for soil investigation complete at Luma, Darke, Lebra and Melchham bridge sites.  Topographic map and general arrangement drawing of Luma Khola and Darke Khola being prepared.
  • Completed 63km length of full width 4.5m wide track opening. Substantial completion of 1km this month taking the total to 41.13 km length.
  • Healthy workforce team conducted 4 outreach clinics in MUG and HUM examining 59 workers including 32 females.
  • Orientation in first aid kit management, risk reduction and Covid 19 prevention organised for SRBGs in MHLR

Monthly PMR – January 2021

  • Detailed engineering survey of 4 small span bridges complete. Bridge design of Luma Khola started. Borehole construction at Luma Khola complete, ongoing at Darke Khola. Identification of quarry site and location for mini aggregate crushing plant initiated by the contractor.
  • Completed 63km length with 4.5m width and substantial completion of 40.20 km length employing 8 excavators.
  • Healthy Workforce Team conducted 4 outreach clinics in MUG and HUM examining 79 workers including 43 females.
  • First Aid Kit orientation organised for 126 participants including 65 females, 4 events. Replenished FAKs in 83 groups.

Monthly PMR – December 2020

  • All field staff remobilised to resume work along the MHLR alignment and in the Covid 19 response component.
  • 8 excavators engaged in log management, spot improvement and backfilling work. Tippers and backhoe mobilised for loading and transporting gravel for spot improvement.
  • 26 km road section from Gamgadhi to Darke Khola completed and handed over to the Provincial government (Dec 25, 2020).
  • UK Aid contracted Resilience MEL Independent Verification Team has verified the substantial completion of the 26km road section and due actions taken by MHLR on their recommendations before the handover.

Trimester Report July – October 2020

This is the sixth trimester report of the FCDO-UK Aid funded Rural Access Programme Phase 3 - Mugu Humla Link Road Project (RAP3-MHLR) since project implementation starting 29th October 2018.  The report covers the period of 1st July to 31st October 2020.  This report summarises information presented in the project’s monthly reports from the trimester, in particular key achievements, results and issues experienced.  It also provides additional information and data on the project that was not relevant for inclusion in the monthly reports, or which it is too onerous to collect on a monthly basis.

Trimester Report March – June 2020

This is the fifth trimester report of the DFID-UK Aid funded Rural Access Programme Phase 3 - Mugu Humla Link Road Project (RAP3-MHLR) since the start of the project implementation (29th October 2018).  The report covers the period of 1st March to 30th June 2020.  This report summarises the information presented in the project’s monthly reports from the trimester, in particular the key achievements, results and issues experienced.  It also provides additional information and data on the project that was not relevant for inclusion in the monthly reports, or which it is too onerous to collect on a monthly basis.

Monthly PMR – November 2020

  • 14 members of staff remobilised after Dashain and 9 after Tihar, to resume work along the MHLR alignment. PST leads and field staff remobilised after Tihar and Chhath to carry out work in the Covid 19 response component.
  • 6 Excavators mobilised in this reporting period, mostly for log-management.
  • During the festivals, the assigned local staff cared for the field offices and stores along MHLR to ensure safety.
  • The Independent Verification Team have completed their visit of the MHLR alignment.

Pages

Subscribe to RSS - RAP3 MHLR