Submitted by admin on

Publish Date:
April 2021
- Conceptual designs for bridges now finalised. Detailed designs for Luma and Darke submitted by Contractor.
- 2 km substantial completion achieved on MHLR this month taking the total to 45.2 km.
- Healthy workforce team conducted 4 outreach clinics in Mugu and Humla examining and providing medicines to 49 workers including 23 women.
- Organised 13 events of orientations on first aid kit management, risk reduction and Covid 19 prevention, nutrition and personal hygiene for S/RBGs in MHLR, where 308 members, including 66 women, benefitted.