Back to top

Monthly PMR – August 2019

Publish Date: 
August 2019
Author: 
  • Fuel stocks are approximately 67,000 litres. Stocks are sufficient for about 2 months of operations.
  • Draft Technical Notes on key Road Alignment Design features, Excavator Management, and Construction of Road Structures have been reviewed / tested by the site teams and final edits in progress.
  • Revised Works Method Statements for Tree Cutting and Management, Safe Handling and Storing of Fuel, and Safe Handling and Operation of Chainsaw are being further tested in the field.
  • Field verification of road alignment and environmental management plans has been conducted. 
  • Plantation of compensatory trees has started.