Monthly PMR – August 2021

Publish Date: 
September 2021
Author: 
  • Contractor submitted final design drawing of all 4 river crossings. Drawings being reviewed before forwarding to DoLI.
  • Contractor’s team reached Gamgadhi to establish site office and identify quarry sites. Sand, stone and aggregate samples collected from Luma and Darke and being brought to Kathmandu for lab testing.
  • Mobilised all SRBGs. 1km substantial completion achieved on MHLR construction taking the total to 50.5km
  • Continued RMG maintenance work between Gamgadhi and Chankheli.
  • Confirmed Internal Verification team’s MHLR field visit dates to verify construction of Darke - Chankheli section before scheduled handover.