Monthly PMR – December 2019

Publish Date: 
January 2020
Author: 
  • Field level activities have been concentrated in the lower altitude section on Mugu side as snow along other sections is too deep for safe access and working. 
  • We have engaged with ex-RAP3 communities in Kalikot and Bajura to seek additional labour to cover the shortage of supply from Mugu and Humla.  Early snowfall means their mobilisation will be deferred until February / March once the worst of the snow clears.
  • Two of the 11 excavators are no longer working – one left to take up other work opportunities, one contract was terminated by RAP3 MHLR due to non-compliance with the hire agreement and code of conduct (working for others while contracted by us and stirring up conflicting views within the local community).