Monthly PMR – December 2020

Publish Date: 
January 2021
Author: 
  • All field staff remobilised to resume work along the MHLR alignment and in the Covid 19 response component.
  • 8 excavators engaged in log management, spot improvement and backfilling work. Tippers and backhoe mobilised for loading and transporting gravel for spot improvement.
  • 26 km road section from Gamgadhi to Darke Khola completed and handed over to the Provincial government (Dec 25, 2020).
  • UK Aid contracted Resilience MEL Independent Verification Team has verified the substantial completion of the 26km road section and due actions taken by MHLR on their recommendations before the handover