- All field staff remobilised to resume work along the MHLR alignment and in the Covid 19 response component.
- 8 excavators engaged in log management, spot improvement and backfilling work. Tippers and backhoe mobilised for loading and transporting gravel for spot improvement.
- 26 km road section from Gamgadhi to Darke Khola completed and handed over to the Provincial government (Dec 25, 2020).
- UK Aid contracted Resilience MEL Independent Verification Team has verified the substantial completion of the 26km road section and due actions taken by MHLR on their recommendations before the handover