- Snow still continues to severely impact on works progress, with limited activities being confined to lower altitude sections.
- 133 S/RBGs and rock drill groups (64 RBGs, 65 SRBGs, and 3 drill groups) are engaged in structures work and rock cutting.
- 1 chainsaw group is engaged on Humla side for tree management.
- 12 Excavators are engaged in track opening and widening.
- Fuel stocks are approximately 30k litres.