- Drill holes for soil investigation complete at Luma, Darke, Lebra and Melchham bridge sites. Topographic map and general arrangement drawing of Luma Khola and Darke Khola being prepared.
- Completed 63km length of full width 4.5m wide track opening. Substantial completion of 1km this month taking the total to 41.13 km length.
- Healthy workforce team conducted 4 outreach clinics in MUG and HUM examining 59 workers including 32 females.
- Orientation in first aid kit management, risk reduction and Covid 19 prevention organised for SRBGs in MHLR