Progress This Month
1.1.
Narrative
·
Started foundation work at Luma Khola Bridge. Contractor has stored materials required for construction and established a material testing lab. Bar bending for foundation works complete.
·
Started aggregate production and dismantling of the wooden bridge at Darke. Gabion retaining walls also being dismantled to lay bridge foundation. Reinforcements required for foundation works prepared.
·
Substantially completed a total of 62.81 km in MHLR construction. 190m structure works remaining.
·
Surface improvement works ongoing between Melchham (52+000) and Janche Khola (Ch 56+880).
·
As-built survey ongoing between Melchhyam and Deuli.
·
Liaising and sharing information with WFP for IV of MHLR completion in March
·
Received approval and budget allocation for carrying out additional Specific Maintenance on RAP3 roads in Mugu and Humla