Monthly PMR – February 2022

Publish Date: 
March 2022
Author: 

1.    

Progress This Month


1.1.  

Narrative


·     

Started foundation work at Luma Khola Bridge. Contractor has stored materials required for construction and established a material testing lab. Bar bending for foundation works complete.    


·     

Started aggregate production and dismantling of the wooden bridge at Darke. Gabion retaining walls also being dismantled to lay bridge foundation. Reinforcements required for foundation works prepared.    


·     

Substantially completed a total of 62.81 km in MHLR construction. 190m structure works remaining.    


·     

Surface improvement works ongoing between Melchham (52+000) and Janche Khola (Ch 56+880).


·     

As-built survey ongoing between Melchhyam and Deuli.


·     

Liaising and sharing information with WFP for IV of MHLR completion in March


·     

Received approval and budget allocation for carrying out additional Specific Maintenance on RAP3 roads in Mugu and Humla