Monthly PMR – January 2020

Publish Date: 
February 2020
Author: 
  • Snow continues to severely impact on works progress, with limited activities being confined to lower altitude sections. 
  • 129 S/RBGs and rock drill groups have been mobilised for structure works and critical rock section at Dhandhuska cliff above Jaanche settlement.
  • Fuel stocks are approximately 50k litres.
  • Healthy workforce health, safety and sanitation programme:  21 events for 216 male and 162 female participants.