- Detailed engineering survey of 4 small span bridges complete. Bridge design of Luma Khola started. Borehole construction at Luma Khola complete, ongoing at Darke Khola. Identification of quarry site and location for mini aggregate crushing plant initiated by the contractor.
- Completed 63km length with 4.5m width and substantial completion of 40.20 km length employing 8 excavators.
- Healthy Workforce Team conducted 4 outreach clinics in MUG and HUM examining 79 workers including 43 females.
- First Aid Kit orientation organised for 126 participants including 65 females, 4 events. Replenished FAKs in 83 groups.