Monthly PMR – June 2021

Publish Date: 
July 2021
Author: 
  • Design drawings and reports of all 4 bridges complete. Independent Checker reviewing these for finalising.
  • 0.48km substantial completion achieved on MHLR construction this month taking the total to 48.41 km.
  • L-section drawing of Chankheli - Saththaple section complete.
  • Healthy workforce team organised 27 orientations on first aid kit management, risk reduction, Covid 19 prevention, nutrition, personal and menstrual hygiene for S/RBGs in MHLR, and family planning and child vaccination, where 382 members, including 100 women, benefitted.
  • Bioengineering works started in different locations along MHLR