- Design drawings and reports of all 4 bridges complete. Independent Checker reviewing these for finalising.
- 0.48km substantial completion achieved on MHLR construction this month taking the total to 48.41 km.
- L-section drawing of Chankheli - Saththaple section complete.
- Healthy workforce team organised 27 orientations on first aid kit management, risk reduction, Covid 19 prevention, nutrition, personal and menstrual hygiene for S/RBGs in MHLR, and family planning and child vaccination, where 382 members, including 100 women, benefitted.
- Bioengineering works started in different locations along MHLR