Monthly PMR – March 2021

Publish Date: 
April 2021
Author: 
  • Lab testing of soil samples from river crossing sites ongoing. Conceptual design drawings submitted by contractor reviewed and comments shared.
  • Completed 63km length of full width (4.5m) track opening. Substantially completed 2 km this month taking the total to 43.2 km length.
  • Healthy workforce team conducted 4 outreach clinics in Mugu and Humla examining and provided medicines to 47 workers including 18 women.
  • Organised 54 orientations on first aid kit management, risk reduction and Covid 19 prevention, for S/RBGs in MHLR, where 798 members, including 192 women, benefitted.