Monthly PMR – May 2022

Publish Date: 
May 2022
Author: 
  • Luma Khola Bridge (Ch-12+500):  Abutment wall complete on both banks (4.8m). Formwork for deck slab laid. Reinforcement bars being tied.    
  • Darke Khola Bridge (Ch-26+020): Abutment wall complete on both banks (3.8m). Formwork for arch slab will start.    
  • Lebra Khola Bridge (Ch-42+700): Left bank - foundation complete; scaffolding for abutment wall reached 2.4m (target 4.6m). Right bank – foundation rebar in place, formwork being placed; ready for concreting.  
  • Melchyam Khola Bridge (Ch-53+170): Left bank: foundation complete; formwork for 2.4m (target 4.6m) abutment wall complete. Right bank – foundation complete; started tying reinforcements for 2.4m abutment wall.