  • Technical training for all MHLR field staff has been conducted, including practical demonstrations.  The training addressed the key issues found during internal audits. 
  • All field level activities restarted, with 64 RBGs (1277 members) and 36 SRBGs (518 members) remobilised. 
  • Mugu Karnali river level has lowered sufficiently to allow tractors to pass allowing transportation of materials in Gamgadhi stores to reach site.
  • The steep and rocky section at Jaanche (Ch58) continues to cause problems and delay track opening works progress.  Labour rock breaking groups have also been mobilised to try to expedite works.