Submitted by admin on

Publish Date:
September 2020
- With the lifting of most travel bans, and securing permissions from the district and local governments, field staff have started mobilising to Mugu and Humla on 26th September, taking necessary precautions. We have secured permission from the CDO, Municipalities and wards to resume work.
- Local staff continue to care for the field offices and stores along MHLR. Seven excavators are working on road widening and surface improvement works along with one backhoe and two tippers.
- 3.43KM surface improvement work is complete.