Monthly PMR - September 2019

Publish Date: 
September 2019
Author: 
  • 3.5m track opening has halted at Janche Khola (Ch58) due to one rocky outcrop and one very hazardous section where extra protection measures (structures between works and houses) need to be installed before works can continue.Fuel stock is approximately 41,600 litres. Transportation of fuel will continue after Tihar to replenish stocks before the anticipated winter road closure.
  • Draft Technical Notes on key Road Alignment Design features, Excavator Management, and Construction of Road Structures have been shared with DFID.  Final checks and revisions are being made before sharing with DoLI.